Commercial, Baku
Baku Harbour Office Campus
- Employer
- Port authority
- Area
- 47,800 m²
- Floors
- 14
- Duration
- 30 months
- Planned handover
- 30.11.2025
- Actual handover
- 30.11.2025
On time
A two-block office campus, handed over on the contract date.
The campus links two port administration buildings around a courtyard. The waterfront ground was reinforced with 22-metre piles.
Piling finished two weeks ahead of plan; the time gained was held as a buffer against wind delays during facade installation.