The sharp edge of the glass facade against the sky.

Commercial, Baku

Baku Harbour Office Campus

Employer
Port authority
Area
47,800 m²
Floors
14
Duration
30 months
Planned handover
30.11.2025
Actual handover
30.11.2025

On time

A two-block office campus, handed over on the contract date.

The campus links two port administration buildings around a courtyard. The waterfront ground was reinforced with 22-metre piles.

Piling finished two weeks ahead of plan; the time gained was held as a buffer against wind delays during facade installation.