Delivery record

Every project we have handed over since 1986, late ones included.

Deliveries with planned and actual dates
ProjectCountryPlannedActualDeviation
Kartaltepe State HospitalTürkiye14.03.202612.03.2026−2 days
Baku Harbour Office CampusAzerbaijan30.11.202530.11.20250 days
Almaty North ResidencesKazakhstan15.09.202524.09.2025+9 days
Batumi Coast HotelGeorgia01.06.202527.05.2025−5 days
Riyadh Vocational Training CampusSaudi Arabia20.02.202518.02.2025−2 days
Levent North Office TowerTürkiye30.09.202430.09.20240 days
Manisa School CampusTürkiye30.04.202427.04.2024−3 days
Medina Public Service BuildingSaudi Arabia04.03.202403.03.2024−1 day
Sakarya Health CampusTürkiye09.01.202431.12.2023−9 days
Tekirdağ Shopping CentreTürkiye26.12.202318.12.2023−8 days
Maslak Cultural CentreTürkiye26.11.202315.11.2023−11 days
Manisa HotelTürkiye24.07.202313.07.2023−11 days
Söğütözü Public Service BuildingTürkiye15.06.202311.06.2023−4 days
Bursa ResidencesTürkiye03.01.202330.12.2022−4 days
Bucharest Cultural CentreRomania01.10.202201.10.20220 days
Sivas HotelTürkiye15.08.202215.08.20220 days
Sakarya Production PlantTürkiye17.07.202216.07.2022−1 day
Etimesgut Training and Research HospitalTürkiye13.05.202206.05.2022−7 days
Kutaisi Health CampusGeorgia07.11.202131.10.2021−7 days
Maslak CourthouseTürkiye08.08.202129.07.2021−10 days
Gebze Office BuildingTürkiye22.06.202120.06.2021−2 days
Eskişehir State HospitalTürkiye03.01.202101.01.2021−2 days
Erzurum CourthouseTürkiye14.11.202007.11.2020−7 days
Trabzon Metro StationTürkiye15.07.202012.08.2020+28 days
Almaty ResidencesKazakhstan21.06.202017.06.2020−4 days

How we count

The planned date is the handover date in the signed contract, updated only by approved change orders. The actual date is the date of the provisional acceptance certificate. Deviation is the number of calendar days between the two.