The hospital's white facade with round windows.

Healthcare, Istanbul

Kartaltepe State Hospital

Employer
Public health authority
Area
64,200 m²
Floors
9
Duration
31 months
Planned handover
14.03.2026
Actual handover
12.03.2026

2 days early

A 412-bed hospital, handed over two days before the contract date.

The hospital holds 412 beds, 14 operating theatres and an emergency block over nine floors. Construction took 31 months; the base-isolated foundation was on the critical path for the first eight.

Mechanical works fell two weeks behind in November 2025. A second shift and prefabricated shaft modules closed the gap by January; the building passed provisional acceptance on 12 March 2026.