Healthcare, Istanbul
Kartaltepe State Hospital
- Employer
- Public health authority
- Area
- 64,200 m²
- Floors
- 9
- Duration
- 31 months
- Planned handover
- 14.03.2026
- Actual handover
- 12.03.2026
2 days early
A 412-bed hospital, handed over two days before the contract date.
The hospital holds 412 beds, 14 operating theatres and an emergency block over nine floors. Construction took 31 months; the base-isolated foundation was on the critical path for the first eight.
Mechanical works fell two weeks behind in November 2025. A second shift and prefabricated shaft modules closed the gap by January; the building passed provisional acceptance on 12 March 2026.